We'll soon be working in the area to replace water mains that supply the neighbourhood.

Why we're doing this

Our work will save water by reducing leakage and burst pipes in the area. It'll also improve the supply and consistency of service to residents.

What's the impact?

We are starting on site in mid September 2015. During our work, there may be some disruption to some customers' water supplies. Planned shut offs will never exceed 4 hours and we will write to you at least 48 hours beforehand to let you know, offer advice and provide bottled water where needed.

During this work there will be changes to parking and traffic management including some temporary traffic lights.

Keeping you informed

Please see below most recent letter to residents.

How long will it take?

We'll be working in the area until late Spring 2017. A more detailed programme is below.

Street Name Location Starting Duration
Amanda Close

From the Copperfield junction to the end of the road

March 8 weeks
The Brambles

From Clayside Junction to the end of the road

February 3 weeks
Copperfield

From Limes Avenue Junction to High Meadows Junction

November 38 weeks
Copperfield

From High Meadows Junction to Trotwood Junction

November 38 weeks
Clayside

From Limes Road Junction to the end of the road

February 3 weeks
Franklyn Gardens From New North Road junction to Franklyn Gardens January 9 weeks
Hazelbrouck Gardens

From the junction of New North Road to 63 Hazelbrouck Gardens

September 8 weeks
High Meadows Copperfield Junction August 7 weeks
Keats Close From Limes Road junction to the end of the road February 3 weeks
Limes Avenue Limes Avenue to outside 60 Limes Avenue August 40 weeks
Limes Avenue Limes Avenue Junction to 230 Limes Avenue August 40 weeks
New North Road 82 New North Road to 192 New North Road October 12 weeks
North Dene At the junction of Copperfield September 8 weeks
Park Area From Junction Manor Road to Copperfield October 6 weeks
Regency Close From Limes Road Junction to the end of the road December 6 weeks
Southdale From Copperfield Junction to Thurlow Gardens Junction December 4 weeks
Thurlow Gardens From the New North Road junction to 23 Thurlow Gardens December 5 weeks
View Close Copperfield Junction July 4 weeks
West Mead From Limes Road Junction to the end of the road March 10 weeks

We like to share as much of our programme with you as possible so that you are as best informed as you can be, but please note that as work begins our programme can sometimes change.

Check back for updates and changes to the programme.