We're replacing over 2.7km of pipes in the Clapham and Battersea area. This upgrade will reduce the chance of bursts and provide a more reliable water supply. This long-term solution will future-proof your water network for generations to come.
This page was last updated on 27 February 2026.
Our work started on Monday 5 January 2026. We'll be working in phases along the road to complete the scheme.
Working hours:
5 January 2026 for around eight weeks
Road closures:
5 January 2026 for around six weeks
Road closures:
19 January 2026 for around eight weeks
Road closures:
2 February 2026 for around nine weeks
Road closure between 76 Bolingbroke Grove and 11 Kelmscott Road
19 February 2026 for around six weeks
Road closure between 31 and 55 Shelgate Road.
20 February 2026 for around six weeks.
Road closure of Clapham Common North side until number 52.
2 March 2026 for around 11 weeks
Road closures:
After phase 6, we’ll test the new water pipe before we connect you to it.
Please note that these dates and durations may be subject to change. We'll notify you if any updates occur, and you can also keep an eye on this webpage for the latest information.
As part of this scheme, we'll also be working on Tregarvon Road and Marmion Road. We'll update you with further information before these works start.
We've now completed works on Adderley Grove, Ashness Road and Bowood Road.
We may also need to turn off your water supply for a short time. If so, we’ll send you a letter with more details at the time.
If you have any questions, please call us on 0800 316 9800 or you can email us. Please quote reference: BB01362341.