Capital delivery major projects pipeline

Our capital delivery major projects pipeline lists our potential procurement activity. This includes the indicative high-level scope information for our major projects.

It’s also published on the government Find a Tender service. 

This is for information only and reflects our anticipated procurement pipeline without commitment.

capital delivery major projects pipeline graph timeline

Project title

Short description

Estimated tender release date

Estimated contract award date

Estimated construction start date

Estimated contract duration (award to takeover)

Estimated contract value (£ ex. VAT)

Likely procurement procedure 

K298: Maple Lodge STW

Increase capacity of STW and storm tanks. Improve quality of final effluent (ammonia and phosphrous).

31 Mar 20251 Feb 20261 Feb 202760 months£140-£280m

UCR ITN to award. Optimising design and programme to fix target cost (two-stage procurement process).

K935: Riverside STW

New assets to meet discharge compliance. Upgrade and/or replacement of existing expired assets.

1 Jun 20251 Feb 20261 Feb 202760 months£120m

UCR ITN to award. Optimising design and programme to fix target cost (two-stage procurement process).

L750: Beckton STW AMP8 WAAP

Replacement and refurbishment of assets. Improve resilience on process quality compliance and major capital maintenance. 

1 Mar 20261 Dec 20261 Jun 202748 months£40m

Most likely two-stage procurement process.

S39830: Beckton STW THP upgrade

Extra thermal hydrolysis plant and associated assets on the sludge treatment stream.

1 Mar 20261 Dec 20261 Jun 202760 months£130m

Most likely two-stage procurement process.

L752: Mogden STW AMP8 WAAP

Replacement and refurbishment of assets. Improve resilience on process quality compliance and major capital maintenance. 

1 Mar 20261 Dec 20261 Jun 202754 months£80m

Most likely two-stage procurement process.

S40439: Didcot STW - Growth, Phosphorus, CHP

New assets to meet growth, new phosphorus quality compliance and new CHP/Gas to Grid.

1 Apr 20261 Jan 20271 Jan 202860 months£110m

Most likely two-stage procurement process.

L479: Hampton Advanced Water Treatment Works (AWTW) UV treatment

New UV treatment process to deactivate Cryptosporidium Oocysts.

1 Jul 20261 Apr 20271 Oct 202730 months£50mMost likely two-stage procurement process.
L844: Ashford UV AWTW UV treatment

New UV treatment process to deactivate Cryptosporidium Oocysts.

1 Jul 20261 Apr 20271 Oct 202730 months£70m

Most likely two-stage procurement process.

S38271: Wantage STW - Growth, phosphorus

New assets to meet growth and new phosphorus quality compliance.

1 Jul 20261 Jan 20271 Oct 202742 months£40m

Most likely two-stage procurement process.

S38971: Reading STW Phosphorus, CHP, WAAP

Replacement and refurbishment of assets to improve resilience or process compliance. New assets to meet phosphorus quality improvement and CHP/Gas to Grid.

1 Oct 20261 Jul 20271 Apr 202848 months£60m

Most likely two-stage procurement process.

S40373: Swindon STW - Sludge growth, phosphorus, pollution

New infrastructure to meet sludge growth, phosphorus quality permit and pollution reduction.

1 Oct 20261 Jul 20271 Apr 202854 months£70m

Most likely two-stage procurement process.

L751: Crossness STW AMP8 WAAP

Replacement and refurbishment of assets. Improve resilience on process quality compliance and major capital maintenance. 

1 Jan 20271 Jul 20271 Feb 202854 months£80mMost likely two-stage procurement process.
S38634: Hogsmill  STW - Phosphorus, CHP & WNI river restoration

New assets to meet phosphorus and river quality improvement and CHP/Gas to Grid.

1 Apr 20271 Jan 20281 Oct 202842 months£60m

Most likely two-stage procurement process.

Express an interest

When specific procurements go live, they will be advertised on the Find a Tender service. To express an interest in any of these, please do so using the Find a Tender service. Simply search for "Thames+Water" to see all our current notices.