Top of main content

Surbiton trunk mains project

We’ve been working to install a new trunk main on the A24. This is a £15m major infrastructure investment to reduce supply interruption and improve water supply. The replacement pipe covers 2.4km along the A24 and is a major part of our clean water network.

We’ll soon be completing the final sections of the trunk main. This involves installing valves and fittings to connect the main to our network.

We’ve had some recent challenges around pressure-testing the new main. We've designed and installed bespoke valves and fittings to overcome this. As a result, we've had to amend the works programme. Our works are on schedule despite this, so we still expect to complete the scheme in July 2025.

We appreciate that these works have been disruptive. We apologise for any additional inconvenience caused by the change of programme.

 This page was last updated on 23 May 2025.

When and where we’ll be working 

Our working hours will be Monday to Friday, 7am to 6pm and weekends 8am to 5pm.

These junctions on the A24 will close as part of the approved traffic management plan:

 

Street name

Start of closure

End of closure

Derinton Road 25 April 2025  8 June 2025 
Lessingham Avenue  25 April 2025  8 June 2025 
Ansell Road 25 April 2025  16 June 2025 
Balham Park Road 7 January 2025 9 July 2025 
Trevelyan Road 13 May 2025  9 July 2025 

How this may affect you

  • We'll continue the connection process at the Balham Park Road junction with Balham High Road. This is the most disruptive of the connection locations on the A24. This is because it's the primary connection site, where all the testing will take place from.  This closure of the junction with the A24 will be extended until 9 July 2025.
  • The junctions of Derinton Road, Ansell Road and Lessingham Avenue will stay closed until 8 June 2025
  • Our next phase will take place near the junctions of Trevelyan Road and Carlwell Street on the A24.  Trevelyan Road junction will be closed until 9 July 2025. We've previously been in this location in 2024 to install the new pipes. We must now complete the connections and commission the pipes into the network.
  • The final phase of work will take place near the junction with Garratt Lane. A lane closure, with two-way traffic maintained at all times, will be in operation for this phase. This starts on 10 July 2025 for two weeks.
  • Access will be maintained for residents and businesses via diversion routes
  • No bus routes are being diverted as a result of these works.
  • You may notice an increase in noise and vehicle movements. We’ll do everything we can to keep this to a minimum by installing sound barriers, where necessary.
map showing area affected by Surbiton trunk mains replacement

The map outlines the area where we'll be replacing the infrastructure

Get in touch

If you have any questions, call us on 0800 316 9800 or email customer.feedback@thameswater.co.uk. Quote number: BB70085755. 

For business customers, please contact your retailer for information relating to our work.

Extra support

Our Priority Services can help provide you or someone you know with extra support.

The service is free and carers, friends, or family can register on behalf of someone else.

Slip lining of 60m successfully completed across the Tooting Bec Station Junction

Sliplining technique being used

Upper Tooting Road launch pit

Upper Tooting road launch pit

LiDAR survey in pipe

Lidar survey

6no. BT ducting that was encased in concrete above the live 30” Cl

6no. BT ducting that was encased in concrete above the live 30” CI