Surbiton trunk mains project

Upcoming disruptive works

Our upcoming work is expected to be disruptive. We're sorry for any inconvenience this causes. 

We're carrying out a £15 million upgrade of our clean water main along the A24. This project is part of our wider work to strengthen and modernise the water network in South London. The scheme will be complete soon.

Work began in July 2024. By December 2024, we had installed a new lining inside the existing trunk main. “Slip lining” means inserting a new pipe inside the old one, which strengthens it and helps prevent future leaks or bursts. This section was completed about 3 months ahead of schedule.

This page was last updated on 24 September 2026.

Challenges

Since January 2025, our teams have focused on connecting the newly lined pipe into the existing water network. One of the most important tasks was to join it to a larger pipe at Balham Park Road.

We overcame significant engineering challenges during this phase of work, completing the connection in May 2025. 

However, we still needed to fit a special valve and chamber. This was to help control how water flows through the network, directing supply where it's needed. As this valve wasn't in our original plan, it had to be custom made.

Testing and connections

After the main connection activity, we needed to test the new section of pipe. This was completed in July 2025. 

Other works in the area

Other major works on the A23 at Streatham Hill in July 2025 meant we needed to demobilise our works on the A24 until January 2026. This was to reduce disruption and impact on traffic.

Works in 2026

Since January 2026, we have been focusing on connecting the new pipe into the existing water network at the south end. This is near Tooting Broadway station. We have also been carrying out smaller connections along the new pipeline for integration into the water network. This will help with the distribution of water in the area.

We are now working on completing the installation of the valve and chamber at the junction with Balham Park Road. Once complete, our new water main can be commissioned into service. 

Next steps

Our current phase of work started on 30 July at the junction with Balham Park Road. There are temporary traffic lights in place on the A24 during this phase.

This complex scheme began in 2024, in collaboration with Wandsworth Council and Transport for London. Working together, we aim to reduce disruption in the area.

We know this work disrupts the community, and we’re sorry for any trouble it causes.

How you'll be affected

  • Temporary 2-way traffic lights are in place on the southbound carriageway from 30 July 2026 
  • We are currently working near Balham High Road, with road closures from 30 July to 8 October 2026
  • Access will be maintained for residents and businesses via diversion routes
  • Bus routes will not be affected
  • You may notice an increase in noise and traffic. We’ll do everything we can to keep this to a minimum by installing sound barriers, where necessary

Please see the table below for the updated junction closures of works along the A24. 

Working hours

Our working hours will be Monday to Friday, 7am to 6pm. Weekends 8am to 5pm.

Street name

Start of closure

End of closure

Balham Park Road

30 July 20268 October 2026

Get in touch

If you have any questions, call us on 0800 316 9800 or email customer.feedback@thameswater.co.uk. Quote number: BB70085755. 

For business customers, please contact your retailer for information relating to our work.

Extra support

Our Priority Services can help provide you or someone you know with extra support.

The service is free and carers, friends, or family can register on behalf of someone else.

Surbiton pipe mains project
Thames Water engineer working on Surbiton mains replacement
Thames Water engineer working on Surbiton mains replacement
Thames Water engineer working on Surbiton mains replacement
Surbiton mains replacement