New River Eade Road Refurbishment
The New River was completed at the start of the 17th century, in 1613, so it isn’t new at all. It’s also not a river: it’s an aqueduct, built to bring drinking water from Hertfordshire to North London.
It remains an essential part of London's water supply, carrying up to 220 million litres over 20 miles along the channel each day for treatment. This represents some eight per cent of London's daily water consumption.
In addition to carrying our water supply, starting in 1992 we worked with local people and organisations to create a 28-mile (45km) path following the course of the New River, linking the inner city with the countryside.
Our New River team are the custodians of this river, with a team that is dedicated to the upkeep of it. Half of our current team have over 30 years’ experience of working on this aqueduct.

Our work
The Eade Road section of the New River Aqueduct is leaking, losing water and gradually eroding the embankment. Small-scale repairs have been carried out to date to maintain the New River.
Previous drainage works have diverted leaked water into the sewer network to prevent flooding along Eade Road but have not addressed the root cause of the leakage. You can view the current assessment of leakage through the New River Embankment flow assessment.
We are looking to refurbish a section of the New River channel at Eade Road, between Green Lanes and Seven Sisters Road, to prevent leakage and extend the life of this key asset.
The intended solution is to install sheet piles on the northern embankment of the New River for the majority of the length, with short concrete-lined sections where we have utility service crossings. You can view a sketch of the solution.

Planned programme
Site preparatory work started in June 2024. The focus was to set up the welfare facilities and prepare the area. The main refurbishment work started in October 2024 and is expected to end in September 2025.
Current programme
We're currently completing the sheet piling towards Seven Sisters Road. We're also making good progress with the sheet piling towards Green Lanes. You can view what our teams are working on each week until the week commencing 12 February.
Planned footway closure
Regrettably, we'll need to close the footway between the Seven Sisters Road entrance and the Green Lanes entrance. This will be from 10 February 2025 for approximately five weeks. We'll carry out essential works during this period. Due to the health and safety for the local community and our site teams, the footway will be closed.
Alternative routes
During the closure, we have identified alternative routes:
- Alternative route one - you can head along Seven Sisters Road
- Alternative route two - you can head along Green Lanes to Hermitage Road, then along Eade Road to Seven Sisters Road
You can view a map of the footpath closure and alternative routes.

Get in touch
If you have any questions about the project, please call us on 0800 316 9800 option one. Please quote BB302191.