Woodford mains replacement

We are investing £6.2m in a programme of works to upgrade more than 50km of ageing Victorian pipes in your area.

As part of this process, we are looking to replace the pipeline in two sections within Newham. They are among the most vulnerable in the entire Thames Water region.. 

Work is expected to take around two years and will affect multiple roads. 

When and where we'll be working

The project starts on Monday 4 August. 

Our working hours will be Monday to Friday 8am to 6pm. We may also work on Saturdays 8am to 1pm if required.

Roads affected

We'll update this information as the project progresses. 

  • Wolseley Road (E7 9PE) - 4 August to 15 September 2025
  • Lucas Avenue (E13 0RL) - 4 August to 5 October 2025
  • Ohio Road (E13 8EL) - 8 August to 12 September 2025
  • Braemar Road (E13 8EH) - 15 August to 10 October 2025
  • Raymond Road (E13 0SP) - 25 August to 27 October 2025
  • Garfield Road (E13 8EN) - 25 August to 3 October 2025
  • Belton Road (E7 9PF) - 15 September to 27 October 2025
  • Mayfield Road (E13 8EJ) - 29 September to 3 November 2025
  • Thorngrove Road (E13 0SH) - 6 October to 8 December 2025
  • Penge Road (E13 0SL) - 27 October to 29 December 2025
  • Lamailia Road (E7 9PH) - 27 October to 8 December 2025
  • Columbia Road (E13 8DH) - 1 November to 6 December 2025
  • Churston Avenue (E13 0RJ - 8 December to 9 March 2026
  • Beauchamp Road (E7 9PD) - 8 December 2025 to 2 February 2026
map of works being completed at woodford

How this may affect you

We would like to apologise for any disruption caused during these essential works. To minimise impact, we're working with Newham Council and the Highways Authority.

You may notice an increase in noise and vehicle movements, but we’ll do everything we can to keep this to a minimum. Access will be maintained for residents, businesses, and emergency vehicles.

Road closures

Wolseley Road will become a two-way road, and we'll work in 100m phases. This will help maximise traffic flow and reduce residential congestion.

Diversion signs will be displayed.

Parking

We'll be implementing parking bay suspensions. Please look out for our on-street and path signage.

Water supply

We may also need to turn off your water supply for a short time. If so, we’ll send you a letter with more details at the time.

Benefits of the project 

The project is part of a £6.2m investment across our region. It will help to: 

  • Reduce the risk of bursts in the area - this will help save large volumes of water every year
  • Strengthen our existing network for delivering life's essential services for years to come. The new plastic pipes we will lay are much stronger than the existing cast-iron pipes.
  • Reduce traffic management disruptions caused by continuous repair and maintenance works.
  • Increase network reliability. The new pipes have a 100-year lifespan. It will help us continue to provide a reliable service now and for future generations.

Get in touch

If you have any questions or concerns, please call us on 0800 316 9800. Select option 1, and quote reference number BB01175613. We’ll keep you informed as work progresses. You can also check this page for updates.

Business customers should contact your retailer for any additional information.

Help us find problems

You can report a range of problems online including leaks, sewer floods or pollution.

Get extra support

Our Priority Services Register can help provide a little extra support.

Website accessibility

Ways to change your settings and make our site more accessible.