Bibury rising main replacement

Bibury is part of the Rising Main Programme to rehabilitate sewers across our area. This is a key element of our five-year asset management plan. As part of this, we're building a new rising main to provide greater resilience to the network.

By upgrading the pipes, we can avoid sudden and disruptive issues in the future. This includes emergency road closures and tankering from the pumping station. It will also help lower the risk of pollution and environmental damage. This will help contribute to cleaner waterways and a healthier local ecosystem.

When and where we're working

We'll be working from 11 August and expect to finish in December 2026. We've detailed when and where we'll be working for preliminary, phases, and reinstatement.

You may be affected by our work during this time, such as traffic disruptions and road closures. We've included links to diversions for each of our phases. We are also anticipating extra vehicle movements and noise. Resident and business access will be maintained throughout. Emergency access will always be prioritised.

Preliminary work

Date: 11 August to 23 September 2025.

Phase One

Date: 16 to 24 September 2025.

Road closure: between Salt Way and B4425 junction.

Phase Two

Date: 24 September to 8 October 2025.

Road closure: between Salt Way and Church Road junction.

Phase Three

Date: 8 October to 12 December 2025.

Road closure: between Church Road and the river crossing.

Reinstatement work

Date: 5 December 2025 to 23 January 2026.

Get in touch

If you have any questions, you can call us on 0800 316 9800. Please select option one and quote: BB01172556.

We've also included Gloucestershire County Highways Works references:

  • MU057B4425THEVICARAGE-01
  • MU057SALTWAY-01
  • MU057THESTREET-01